Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags
DOI:
https://doi.org/10.1609/aaai.v39i25.34854Abstract
This study investigates scheduling strategies for the stochastic resource-constrained project scheduling problem with maximal time lags (SRCPSP/max). Recent advances in Constraint Programming (CP) and Temporal Networks have re-invoked interest in evaluating the advantages and drawbacks of various proactive and reactive scheduling methods. First, we present a new, CP-based fully proactive method. Second, we show how a reactive approach can be constructed using an online rescheduling procedure. A third contribution is based on partial order schedules and uses Simple Temporal Networks with Uncertainty (STNUs). Our statistical analysis shows that the STNU-based algorithm performs best in terms of solution quality, while also showing good relative offline and online computation timeDownloads
Published
2025-04-11
How to Cite
Houten, K. van den, Planken, L., Freydell, E., Tax, D. M., & Weerdt, M. de. (2025). Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags. Proceedings of the AAAI Conference on Artificial Intelligence, 39(25), 26534–26541. https://doi.org/10.1609/aaai.v39i25.34854
Issue
Section
AAAI Technical Track on Planning, Routing, and Scheduling